Isometric sketch of a terminal: departures from curbside through check-in, emigration, security, lounge and gate to the aircraft, and arrivals from the aircraft through immigration, baggage reclaim and customs control to the landside concourse, parking and taxis

Airport Terminal Consultancy · UAE

“Form follows function.”Louis Sullivan, 1896

In no other building type is this more true than in an airport terminal.

The mission is to ensure that Terminal facilities, new or existing, are clear for users, workable for operators and safeguarded for future growth.

Terminals outlive the operations they were designed for, as technology, passenger behaviour and stakeholder requirements keep changing.

To prepare for that change, a clear framework is needed that defines the operational outcome and the operator’s vision, whether the terminal is new or already in use.

That framework is the Concept of Operations. From it, planning, design and optimisation keep stakeholders aligned around the same outcome.

Services for new and existing terminals

Whether you need implementation solutions and answers to your operational problems, or a third-party independent review, the services REVICO offers are defined below.

  • StrategySet the direction
  • DefinitionTurn it into project outputs
  • ValidationTest it before it’s built

Concept of Operations

The Concept of Operations translates the strategic vision into an operational framework that guides design and operators, ensuring alignment. It is a living document, updated as technology, passenger behaviour and stakeholder requirements change.

What you get

  • Definition of the operational vision and process flows for all terminal users and relevant stakeholders
  • Key interfaces with landside and apron airside infrastructure to ensure alignment
  • KPIs and service levels, with operational requirements captured for each asset processor
  • Interfaces and responsibilities across terminal stakeholders

Stakeholder Engagement

Workshops and work reviews with airport operators, authorities, airlines and design teams, so decisions are made once and implemented. Stakeholder engagement starts at project inception and continues through the design stages, identifying which stakeholders need to be involved so their requirements shape the design and misalignment is avoided down the line.

What you get

  • Planning and operational workshops with operators, authorities, airlines and design teams
  • Layout reviews in real time, with clear operational comments and mark-ups
  • Expert planning input to client and design-team meetings
  • Agreed requirements recorded in one place
  • Multidisciplinary teams coordinated around one set of solutions, from concept to technical design
  • Presence on site with the client's operational team where the project calls for it

Facility Requirements

Static models convert DDFS forecasts into the areas and processor numbers a terminal needs to safely and efficiently process passenger demand. This also includes toilet calculations, vertical circulation and gate sizing, using IATA ADRM formulae and best practice calculation methods.

What you get

  • Define peak hour passengers based on DDFS rolling-hour passenger data
  • Space and processor requirement models for the major processors, on departures, arrivals and transfers as well as staff, goods and waste processors, built from forecasts and design-day profiles
  • Toilet requirements and vertical circulation core capacity, with other support areas
  • Departures lounge occupancy that supports retail net lettable area
  • Schedules of areas ready to go straight into the design brief

Functional Planning

Flow maps for Passengers and Members of the Public, Airport Staff, and Goods-In and Waste-Out, with processor, transfer and baggage strategies that give the design its operational logic. Functional planning turns an operational idea into a layout that works, ending with the processors, areas and adjacencies the design team can draw.

What you get

  • Passengers and Members of the Public flow implementation in the design, with journey analysis through all relevant facilities in the terminal, on departures, arrivals and transfers
  • Airport Staff work-related flow implementation in the design, across all relevant facilities in the terminal and interfaces outside it
  • Goods-In and Waste-Out flow implementation in the design: deliveries, back-of-house routes and waste removal
  • Operational mark-ups and sketches that improve layouts inside the design team's own drawings
  • Terminal input to the airport Master Plan: terminal sizing, passenger-flow strategies and operational requirements across the major processing areas

Dynamic Simulation

A terminal layout, new or existing, is tested with dynamic simulation tools (CAST Terminal) to find where potential bottlenecks are and to ensure the design is compliant with the KPIs.

What you get

  • End-to-end terminal simulation models in CAST Terminal, built in phases, with forecasts and demand profiles tested
  • Visualisation of peak hours throughout all the key processors in the terminal
  • Reactive and proactive behaviour at each processor to understand staffing needs
  • Departures lounge scenarios, including call-to-gate timing and passenger behaviour
  • Choke points found before they are built in, escalator directions optimised and contingencies tested
  • Layout options compared and validated at concept and detailed design stages

Process Optimisation

How a terminal performs, today or in the proposed design, and identify where processors can improve operational efficiency and deliver a better passenger experience, with a practical route to getting there.

What you get

  • Passenger, baggage and staff processes reviewed against demand and service levels
  • Review of proposed layouts and planning documents against IATA planning principles
  • Re-planning of live areas such as arrivals, departures and transfer processors
  • Review existing flows and identify potential cross-flows to prevent congestion
  • Phasing plans and interim layouts that keep the terminal operating during enabling works and construction
  • Options tested in simulation before the client commits

Capability statement

One page for tenders and pre-qualification: services, experience, licence and contact details.

Download PDF

How it works

A short insight into the approach methodology defined through four simple steps, repeated at the design milestones to ensure alignment with expectations.

  1. Define the scope

    The project, its design stage and its stakeholders are identified, and the services and expected outcomes are agreed before work starts.

  2. Understand the requirements

    Operational needs, forecasts, standards and stakeholder expectations are gathered and translated into clear, measurable requirements.

  3. Planning and implementation

    The requirements are developed into planning and design solutions, tested against the agreed outcomes and carried into the design team’s work.

  4. Align and update

    Stakeholders review the work at each design milestone, and requirements, decisions and documents are updated to stay aligned with expectations.

Cristian Weber, founder of REVICO

The specialist behind the work

Cristian’s background is in architecture. He has specialised in airport terminals since 2015 and has been a registered architect in Romania and the United Kingdom since 2019, focusing on functional, operational and capacity planning at the intersection of strategy, design and operations. He started his career in the UK and moved to the UAE in 2024.

He has contributed to competition-winning and delivery-focused multidisciplinary teams, and has led tasks on international airports, from small airports to mega-hubs, as well as on private aviation facilities, shaping terminal strategy from early vision through to technical design.

In 2026 he founded REVICO to bring that experience directly to airport operators, airport developers, design teams and consultancies.

He also contributed to Jacobs’ published paper “Urban Air Mobility: Is it still up in the air for cities?” (November 2022), defining the operational and planning parameters of vertiports.

His work is built on strategic decision-making: the operational outcome is defined first through the Concept of Operations (ConOps), then guides planning and design choices, so the terminal delivers on its vision in daily operation and as it grows.

REVICO is deliberately small and senior-led: you work directly with Cristian, with clear accountability and fast, informed decisions from first workshop to final deliverable.

Cristian Weber

Founder · Airport Terminal SME

Experience on terminals that carry millions

From regional terminals to the master planning of new mega‑hubs, the experience behind the Founder spans the Middle East, Europe and Asia.

Projects led or delivered by the founder, Cristian Weber, in previous roles, can be viewed below.

The need

Challenges

Approach

Outcome